COMMUNITY UPDATES

March 23, 2015

Argento March 2015 Construction Update

The structural concrete pour at our Argento community is now complete and the exterior brick for the townhomes is scheduled to commence in April. Window installations are currently on the 27th floor and the crane removal for the community is … Continue reading

March 20, 2015

Avani at Metrogate March 2015 Construction Update

Our construction teams at Avani at Metrogate are currently pouring concrete on the 3rd floor of the community; having completed 90% of the concrete slab and 80% of the walls on this floor. The plumbing and electrical sleeving and pipe … Continue reading

March 20, 2015

Two Old Mill March 2015 Construction Update

The precast and window installations are now 100% complete at our Two Old Mill community. Drywall is currently being installed on the 8th floor, kitchen installations are on the 5th floor and plumbing and electrical rough-ins are in progress on … Continue reading

March 20, 2015

Ten York March 2015 Construction Update

We are moving on up! Our construction teams have completed pouring concrete on the P5 parking level at Ten York. They are now in the process of finishing the P4 level and have begun pouring on the P3 level. Watch … Continue reading

March 19, 2015

One Old Mill March 2015 Construction Update

Closings are currently taking place on the 9th floor at the One Old Mill community while Homeowner Orientation inspections are being finalized on the 11th floor. All common areas and amenities have been completed with the exception of the corridor … Continue reading

March 19, 2015

Aqualina at Bayside March 2015 Construction Update

Our construction team at Aqualina at Bayside is currently working on the shoring of the construction site and will begin excavation in the upcoming months. Shoring of the construction site is comprised of a caisson wall, which is a series … Continue reading

March 16, 2015

Alto & Parkside at Atria March 2015 Construction Update

The pouring of the ground floor has been completed for both Alto and Parkside at Atria. The second floor pour for Parkside is 60% complete while the second floor pour for Alto is 30% complete. Both precast and window fabrication … Continue reading

February 25, 2015

Argento February 2015 Construction Update

Our construction teams at Argento are working hard to prepare the community for the start of occupancy. Concrete is currently being poured on the roof, window installations are on the 23rd floor and the wood framing for the townhomes is … Continue reading

February 13, 2015

Family Day Long Weekend & Tridel Holiday Hours

It’s Family Day long weekend and this year, it promises to be a chilly one!  Here at Tridel, our Presentation Centres will be open from 12 noon to 6 pm, Saturday, Sunday and Monday.   So if you?re planning to stay … Continue reading

February 05, 2015

Winter Living and Comfort in your Condominium Home

    If you have lived in a house, you probably know all about cold weather preparation for your home, things like getting out the snow shovel and checking the seals on your windows or shutting off the water to … Continue reading

January 28, 2015

Avani at Metrogate January 2015 Construction Update

Our construction teams at Avani at Metrogate are currently pouring concrete for the third floor of the community. The community now has temporary power, and we are working with Enbridge for gas services. Our teams expect to start precast (which … Continue reading

January 23, 2015

Alto & Parkside at Atria January 2015 Construction Update

The P1 parking level at our Parkside building has been completed and the pouring of the ground floor level is now 60% complete. At Alto, the P1 parking garage is 90% complete and the ground floor level is at 25%. … Continue reading

January 21, 2015

Ten York January 2015 Construction Update

With the completion of the excavation at our Ten York community our construction teams have now erected the 2nd crane. With both cranes in place the forming of the P4 and P5 parking levels have commenced. Watch the progress online as … Continue reading

January 20, 2015

Two Old Mill January 2015 Construction Update

The precast and window installations are 99% complete at our Two Old Mill community. Drywall is currently being installed on the 5th floor, kitchen installations are on the 2nd floor and plumbing and electrical rough-ins are being completed on the … Continue reading

January 19, 2015

One Old Mill January 2015 Construction Update

Closings are currently taking place on the 5th floor at our One Old Mill community while Homeowner Orientation inspections are being done on the 7th floor. Drywall is currently being installed on the Grand Penthouse floor while corridor finishes are … Continue reading